undefined

Agenda item

Community Infrastructure Levy: Proposed Spending & Revision of CIL Spending Protocol

Minutes:

Councillor Turner presented a report providing detail on the bids received following the CIL Bidding Process and seeking the approval of a revised CIL Spending Protocol.

 

She drew Cabinet’s attention to a revised recommendation to award St Faith’s Church Havant £21.5k towards making the church accessible to all.

 

Cabinet had mixed opinions around the merits of awarding CIL funding to St Faith’s Church.  Whilst Cabinet acknowledged that St Faith’s was viewed as the Civic Church for the Borough and open to all faiths, the Council’s policy on CIL spending precluded awarding funding to places of worship. 

 

Cabinet also discussed the merits of the proposed highways scheme for Hambledon Road, which some members did not feel was necessary.  During the discussion it was explained that highways works were often put forward by highways engineers and based upon identified needs.

 

Councillor Turner proposed the following amendment to the third recommendation:

 

iii) The Council invest the available Neighbourhood Portion funds as at 

     31 March 2018 outlined in Table D in the capital infrastructure     

     projects:

 

Title and bid reference number

Amount

Requested

Proposed Spend

Cumulative Amount

HIADS Ltd (Replacement Lobby) (D)

£45K

£22,500

£22,500

Age Concern Kitchen Renovation (F)

£27K

£22,962

£45,462

Bidbury Infants School Lighting Project (H)

£19K

£9,500

£54,962

Hayling Sports Centre Extension Feasibility (I)

£18K

£18,000

£72,962

Acorn Centre Extension (J)

£51K

£19,000

£91,962

Church Access Project: Making St Faith’s Accessible to All (C)

£21.5K

£21,500

£113,462

Table D: Current recommended spends and cumulative effect on Neighbourhood Portion if all spending options are supported

 

This proposal was duly seconded by Cllr Pike.

 

Following a vote this amendment was declared LOST, 2 Councillors voting FOR the amendment and 3 Councillors voting AGAINST the amendment.

 

The Leader proposed the recommendation as set out in the report, which was duly seconded by Cllr Turner.

 

Following a vote the recommendation was declared CARRIED, 4 Councillors voting FOR the recommendation and 1 Councillor voting AGAINST the recommendation.

 

It was therefore RECOMMENDED to full Council that:

 

(1) The Council invest the available 123 List CIL funds as at 31 March 2018 in 

      the capital infrastructure projects outlined in Table A:

 

 

Title and bid reference number

 

Amount

 

Cumulative amount

Langstone FCERM Scheme (1)

£575,000

£575,000

Hayling FCERM Strategy (2)

£0*

£575,000

Hooks Row - Shared Pedestrian and Cycle Link (16)

£115,000

£690,000

Park Road Corridor Feasibility (3)

£10,000

£700,000

Elmleigh Road - Pedestrian and Cycle Improvement (4)

£269,000

£969,000

Waterlooville Town Centre London Road Shared Cycleway (5)

£16,000

£985,000

Milton Road Roundabout - Accessibility and Safety (6)

£100,000

£1,085,000

Hambledon Road - Provision of Cycle Route (7)

£60,000

£1,145,000

Warblington Interchange - Feasibility (13)

£12,000

£1,157,000

 

Table A: Current recommended spends and cumulative effect on 123 CIL Pot if all spending options are supported

 

* Funds are not required for this round of CIL Spending but a future commitment is needed to support the spending of CIL Funds in accordance with Table C outlined below.  See also Paragraph 6.3

 

(2) To commit future 123 Pot funds to the following capital infrastructure 

      projects outlined in Tables B and C and that the balance of the CIL  

     123 Pot be retained to contribute to this expenditure:

 

Langstone FCERM Scheme – CIL Pot Building Request 2018-2022

Year

2018/19

2019/20

2020/21

2021/22

Total

CIL funding ‘Pot Building’ – Inc. 60% Risk

 

575,000

 

575,000

 

700,000

 

700,000

 

2,550,000

 

CIL funding – No Risk

 

 

359,375

 

359,375

 

437,500

 

437,500

 

1,593,750

 

Table B: Spending commitment requirement for Langstone FCERM Strategy

 

Hayling Island FCERM Strategy – CIL Pot Building Request 2018-2022

Year

2018/19

2019/20

2020/21

2021/22

Total

CIL funding Pot Building request 30%Risk

 

0

 

170,700

 

262,218

 

100,082

 

533,000

CIL funding – No Risk

 

0

131,308

201,706

76,986

410,000

Table C: Spending Commitment for Hayling FCERM Scheme

 

(3) The Council invest the available Neighbourhood Portion funds as at 31 

      March 2018 outlined in Table D in the capital infrastructure projects:

 

 

Title and bid reference number

Amount

Requested

Proposed Spend

Cumulative Amount

HIADS Ltd (Replacement Lobby) (D)

£45K

£22,500

£22,500

Age Concern Kitchen Renovation (F)

£27K

£22,962

£45,462

Bidbury Infants School Lighting Project (H)

£19K

£9,500

£54,962

Hayling Sports Centre Extension Feasibility (I)

£18K

£18,000

£72,962

Acorn Centre Extension (J)

£51K

£19,000

£91,962

Table D: Current recommended spends and cumulative effect on Neighbourhood Portion if all spending options are supported

 

 

(4)     The CIL Protocol be updated to reflect current practice in view of lessons learned; and

 

(5)     The Council enter a formal agreement with Network Rail to spend £150K on feasibility only in respect of the Warblington Footbridge CIL Spend as agreed by Council on the 21 February 2018.

 

Councillor Bains left the meeting.

Supporting documents: